This post was originally published on this site
Crews will be removing asphalt and pavement and then placing base, rebar and concrete on the northbound (NB) I-405/ Westbound (WB) SR-22 connector. This work will require a long term lane reduction.
The connector will be reduced to one lane beginning as early as 10 p.m. March 14, for approximately two weeks.
Activities will be scheduled 7 a.m. to 4 p.m. Crews may mobilize equipment as early as 6 a.m., and some activities may occur from 9 p.m. to 6 a.m. as needed.
Please be advised that this work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Este trabajo puede ser ruidoso. El horario está sujeto a cambios debido a las inclemencias del tiempo o problemas operativos imprevistos.