I-405 Improvement Project construction alert: Week of Monday, October 17, 2022

This post was originally published on this site

For more information about this project, please contact the 405 Community Outreach Team at [email protected] or 888-400-8994, or visit octa.net/405improvement.

Si prefiere recibir información en español, por favor llame este numero 888-400-8994.

Nếu quý vị muốn nhận được thông tin này bằng tiếng Việt, xin vui lòng liên lạc với cô Lý Gia 888-662-6569.

To view and print a detailed list of closures and detours CLICK HERE!

NOW OPEN! Northbound (NB) I-405 Loop On-Ramp from Harbor Boulevard

We are thrilled to announce another project milestone! The NB I-405 loop on-ramp from Harbor Boulevard is NOW OPEN! Intermittent nightly closures of the ramp are anticipated.

The 405 Community Outreach Team will provide updates in future alerts.

Follow us on social media or sign up for alerts at bit.ly/405-signup to receive the latest project updates and milestones!

UPDATE! Southbound (SB) I-405 Closures Continue for Springdale Street Bridge Falsework Installation

Southbound (SB) I-405 will close between the SB I-405 off-ramp to Springdale Street and the SB I-405 on-ramp from Westminster Boulevard to install falsework for the Springdale bridge.

The SB I-405 closures are anticipated as early as 11 p.m. to 5 a.m. Monday, Oct. 17, to Thursday, Oct. 20, and again 11 p.m. to 6 a.m. Friday, Oct. 21.

Sign up for project-wide and bridge-specific construction alerts at bit.ly/405-signup.

NEW! Southbound (SB) I-405 Closures to Remove Falsework from the I-405/SR-73 Express Lanes Connector

Southbound (SB) I-405 will close between the SB I-405 off-ramp to Fairview Road and the SB I-405 on-ramp from Bristol Street to remove falsework from the new I-405/SR-73 Express Lanes Connector.

The nightly SB I-405 closure are anticipated as early as 11 p.m. to 5 a.m. Monday, Oct. 17, and again on Tuesday, Oct. 18.

Sign up for project-wide and bridge-specific construction alerts at bit.ly/405-signup.

NEW! Northbound (NB) I-405 Closures for Bolsa Avenue Falsework Removal

Northbound (NB) I-405 will close between the NB I-405 off-ramp to Beach Boulevard and the NB I-405 loop on-ramp from Goldenwest Street to remove the falsework from the Bolsa Avenue bridge.

The nightly NB I-405 closures are anticipated as early as 11 p.m. to 5 a.m., Tuesday, Oct. 18, to Thursday, Oct. 20, and again 11 p.m. to 6 a.m. Friday, Oct. 21.

Sign up for project-wide and bridge-specific construction alerts at bit.ly/405-signup.

NEW! Northbound (NB) I-405 Closures to Remove Falsework from the I-405/SR-73 Express Lanes Connector

Northbound (NB) I-405 will close between the NB I-405 off-ramp to South Coast Drive and the NB I-405 loop on-ramp from Harbor Boulevard to remove falsework from the new I-405/SR-73 Express Lanes Connector.

The nightly NB I-405 closure are anticipated as early as 11 p.m. to 5 a.m. Wednesday, Oct. 19, and again on Thursday, Oct. 20.

Sign up for project-wide and bridge-specific construction alerts at bit.ly/405-signup.

REMINDER! Euclid Street Lane Reductions for Center Median Work

Crews will construct the center median on Euclid Street between Newhope Street and Mt. Washington Street.

This work requires Euclid to be reduced to two lanes in each direction at Newhope. The left-turn lane from southbound Euclid to eastbound Mt. Washington will also be closed.

The extended lane reductions are expected to continue through 8 p.m. Monday, Oct. 17.

OPENING SOON! Southbound (SB) I-405 Off-Ramp to Seal Beach Boulevard is Anticipated to Open Soon

Crews closed the SB I-405 off-ramp to Seal Beach Boulevard as part of project improvements.

The ramp closed Sept. 16, and is expected to reopen next week!

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Este trabajo puede ser ruidoso. El horario está sujeto a cambios debido a las inclemencias del tiempo o problemas operativos imprevistos.

Xin lưu ý là công việc này có thể gây nên những tiếng động ồn ào. Lịch trình có thể thay đổi vì thời tiết xấu hoặc những yếu tố công tác không thể dự đoán.

Construction Activities

Montecito Channel

REMINDER! Crews are relocating several utilities to continue widening the drainage channel adjacent to homes in the College Park West community.

Utility line relocation is ongoing, 7 a.m. to 4 p.m. on weekdays.

Block wall installation is anticipated to begin later this fall.

Crews may access the work zone intermittently along College Park Drive and from the WB SR-22 connector to mobilize equipment as early as 6 a.m., and some activities may occur at night from 9 p.m. to 6 a.m. as needed.

Please be advised that this work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

North Gate Road

REMINDER! Crews closed North Gate Road to conduct sewer work.

Vehicles, bicyclists and pedestrians are being detoured to Golden Rain Road to enter and exit Leisure World.

North Gate is anticipated to open in late October.

Please be advised that this work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Springdale Street

REMINDER! Crews will continue reconstructing the sidewalk on the southeast corner of Westminster Boulevard/Springdale. Activities will include curb, gutter and electrical work.

Pedestrian access will be closed on the southeast corner during construction and a detour will be in place.

Construction activities are anticipated to be ongoing through Friday, Nov. 4, 7 a.m. to 4 p.m. on weekdays and Saturdays as needed.

Crews may mobilize equipment as early as 6 a.m., and some activities may occur from 9 p.m. to 6 a.m. as needed.

Please be advised that this work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

The duration of this work may change depending on site conditions. Please be advised that this work may be loud. Dates and times are subject to change due to unforeseen operational factors or inclement weather.